POWER COSTS FOR WIND AND WATER TURBINES
Because there is no
potential for wind turbines in the southeastern states, the only reason for
comparing well-placed wind-turbine systems to well-placed Gulf Stream Turbines
is to see how their profits would compare.
The figures reveal that the Gulf Stream Turbines would produce
substantially better returns than investments in wind turbines.
Although the prices for wind systems can vary with tower heights, rotor diameters and local specifications, the average price for large, modern wind farms is about $1,000 per kilowatt of the rated power installed. As of February 1998, a typical 600 kW wind system would cost between $400,000 and $650,000. Installation costs include foundations (normally made of armed concrete), road construction to move the turbines and the sections of the tower to the building site, a transformer (necessary to convert the low voltage current from the turbines to 10,000 to 30,000 volt for the electrical grid), telephone connections for remote control and surveillance of the turbine, and costs for the cable that will transmit the power to the local power line. Obviously, all these costs depend on the terrain and the distances involved. Remote wind sites result in additional transmission lines, which can cost as much as $300,000 to $1 million per mile. The economics of transmission for these systems is usually poor because, although the line must be sized for the peak output, wind power’s low capacity factor ensures serious underutilization.
Depending on the design and the
materials used in their construction, the individual
The cost per
kilowatt hour for the following graph were calculated based on the cost
per kilowatt of generating capacity being adjusted for the capacity
factors. The capacity factors (CF), the
costs per kilowatt of rated capacity and the operational efficiencies are indicated in the
schedule on the right. All the costs per
kilowatt of generating capacity are amortized over a 20-year period at an
interest rate of 7.5%. These cost comparisons
are based on those capacity factors that can be expected for turbines placed in
the

The
following tables show the costs per kilowatt-hour for
Cost per kWh for
per kW of Rated Capacity
Spread over 12 years
capacity
factor 0.0% 7.5% 9.0% 10.0% 12.0%
90% .0106 .0201 .0220 .0233 .0258
80% .0119 .0226
.0247 .0262 .0290
70% .0136 .0258 .0283 .0299 .0332
Spread over 20 years
capacity
factor 0.0% 7.5% 9.0% 10.0% 12.0%
90% .0063 .0159 .0176 .0190 .0216
80% .0071 .0178 .0200 .0214 .0243
70% .0082 .0204 .0228 .0245 .0277
The
following tables shows the costs per kilowatt-hour for
wind turbines with capacity factors of 23%, 25%, 27% and 30% with capital costs
per kilowatt of rated capacity of $1,000.
These tables are also based on spreading the costs over 12 and 20 years
and a capital return of the percentages listed.
Cost per kWh for
Wind Turbines Based on Cost of $1,000
per kW of Rated Capacity
Spread over 12 years
capacity
factor 0.0% 7.5% 9.0% 10.0% 12.0%
30% .0317 .0602 .0660 .0698 .0774
27% .0352 .0669 .0734 .0775 .0860
25% .0380 .0723 .0791 .0837 .0928
23% .0414 .0786 .0860 .0910 .1009
Spread over 20 years
capacity
factor
0.0% 7.5% 9.0% 10.0% 12.0%
30% .0190 .0476 .0533 .0571 .0647
27% .0211 .0528 .0592 .0634 .0719
25% .0228 .0570 .0639 .0685 .0776
23% .0248 .0620
.0695 .0745 .0844
To cover surges in the demand for
electricity, base load generators today are backed by both “spinning” and
“non-spinning” operating reserves, provided mostly by gas-fired peaker plants.
Typically, one-half of system’s operating reserves are spinning, so that
a sudden loss of generation will not result in a loss of load, with the balance
of the operating reserve available to go on line within ten minutes. Wind generated power is unpredictable. Any probable load or generation variations
that cannot be forecast must be considered when determining the amount of
operating reserve to carry. At present
wind plant penetration levels in